| Item | Last Replaced | Estimated Next Replacement | Description/Notes |
|---|---|---|---|
| Reserve Study *Non-Statutory Reserves | 2020 | 2030 | Completed 2020 |
| Insurance Appraisal *Replacement Costs | 2021 | 2030 | Completed 2021 |
| Wind Mitigations *Roof Only | 2021/2022 | 2036/2037 | Completed 2022 |
| Fiber Internet Infrastructure | 2021 | N/A | Completed 2021 |
| Entrance Gate | Attempt in Progress | ||
| Entrance Monuments Stucco | 2022 | 2072 | In Progress |
| Entrance Landscaping | 2022 | 2051 | Scheduled 2022 |
| Pool Resurface | 2022 | 2032 | Scheduled 2022 |
| Pool Deck | 2018 | 2030 | Completed 2018 |
| Pool Patio Furniture | 2020 | 2030 | Completed 2020 |
| Pool Awning Covers | 2018 | 2030 | Completed 2018 |
| Pool Awning Frames | 2018 | 2040 | Completed 2018 |
| Pool Fence/Gates | 2014 | 2041 | Completed 2014 |
| Pool Club House Paint | 2022 | 2032 | In Progress |
| Pool Club House Screen Enclosure | 2002 | 2032 | Completed 2002 |
| Pool Club House Shingle Roof | 2005 | 2035 | Completed 2005 |
| Pool Bathrooms Remodel | ???? | 2023 | Planned for 2023 |
| Roof – Flat Roof Replacement | 2021/2022 | 2036/2037 | Completed 2022 |
| Roof – Mansard Roof Replacement | 2004 | 2054 | Completed 2004 |
| Building Security Lights | 2021/2022 | 2051/2052 | Completed 2021 |
| Building Electric Risers | 2021/2022 | 2051/2052 | In Progress |
| Building Patio Fences | 2022 | 2052 | In Progress |
| Building/Unit Signs | 2022 | 2052 | In Progress |
| Building Paint | 2011 | 2025 | Completed 2015 |
| Community Road Paving | 2022 | 2052 | Scheduled 2022 |
| Community Signs – Speed Limit, Parking by Permit Only, No Trespassing/Stop Signs | 2022 | 2052 | In Progress |
| Community Perimeter Fence along Shiloh | ??? | 2072 | Scheduled 2022 |
| Community Mail Boxes | 2006 | 2046 | Completed 2006 |
| Community Security Cameras | 2022 | 2052 | In Progress |
| Community Golf Cart | 2016 | 2026 | Purchased 2016 – serviced annually |
| Community Backflows | 2022 | 2062 | Completed 2022 |
| Community Fire Hydrants | 2022 | 2062 | Completed 2022 |
| Community Water Shut Offs | 2022 | 2062 | Scheduled 2022 |
| Community Storage Shed | 2016 | 2046 | Purchased 2016 |
| Community Playgrounds | 2022/2023 | 2052/2053 | Planned replacement 2022/2023 |
Updated May 3rd 2023 – I posted this old version just to see the 2022 list of items and updated items that have been completed and others that are being worked currently.
| Item | Last Replaced | Estimated Next Replacement | Description/Notes |
|---|---|---|---|
| Reserve Study *Non-Statutory Reserves | 2020 | 2030 | Completed 2020 |
| Insurance Appraisal *Replacement Costs | 2021 | 2030 | Completed 2021 |
| Insurance Renewal | 2023 | In Progress Now | |
| Wind Mitigations *Roof Only | 2021/2022 | 2036/2037 | Completed 2022 |
| | |||
| Fiber Internet Infrastructure | 2021 | N/A | Completed 2021 |
| | |||
| Entrance Gate | | | Being looked at |
| Entrance Monuments Stucco | 2022 | 2072 | Completed |
| Entrance Landscaping | 2022 | 2051 | Scheduled 2022 |
| | |||
| Pool Resurface | 2022 | 2032 | In Progress Now |
| Pool Deck | 2018 | 2030 | Completed 2018 |
| Pool Patio Furniture | 2020 | 2030 | Completed 2020 |
| Pool Awning Covers | 2018 | 2030 | Completed 2018 |
| Pool Awning Frames | 2018 | 2040 | Completed 2018 |
| Pool Fence/Gates | 2014 | 2041 | Completed 2014 |
| Pool Club House Paint | 2022 | 2032 | In Progress Now |
| Pool Club House Screen Enclosure | 2002 | 2032 | Completed 2002 |
| Pool Club House Shingle Roof | 2005 | 2035 | Completed 2005 |
| Pool Bathrooms Remodel | ???? | 2023 | Planned for 2023 |
| Pool Club House Replacement Lights | 2023 | In Progress Now | |
| | |||
| Roof – Flat Roof Replacement | 2021/2022 | 2036/2037 | Completed 2022 |
| Roof – Mansard Roof Replacement | 2004 | 2054 | Completed 2004 |
| | |||
| Building Security Lights | 2021/2022 | 2051/2052 | Completed 2021 |
| Building Electric Risers | 2021/2022 | 2051/2052 | Completed 2023 |
| Building Patio Fences | 2022 | 2052 | Completed 2023 |
| Building/Unit Signs | 2022 | 2052 | Completed 2023 |
| Building Paint | 2011 | 2025 | Completed 2015 |
| | |||
| Community Road Paving | 2022 | 2052 | Scheduled 2022 |
| Community Signs – Speed Limit, Parking by Permit Only, No Trespassing/Stop Signs | 2022 | 2052 | In Progress |
| Community Perimeter Fence along Shiloh | ??? | 2072 | Completed 2023 |
| Community Mail Boxes | 2006 | 2046 | Completed 2006 |
| Community Mail Boxes Parcel Locker Repair | 2006 | 2023 | In Progress |
| Community Security Cameras | 2022 | 2052 | In Progress |
| Community Golf Cart | 2016 | 2026 | Purchased 2016 – serviced annually |
| Community Backflows | 2022 | 2062 | Completed 2022 |
| Community Fire Hydrants | 2022 | 2062 | Completed 2022 |
| Community Water Shut Offs | 2022 | 2062 | Scheduled 2022 researching |
| Community Storage Shed | 2016 | 2046 | Purchased 2016 |
| Community Playgrounds | 2022/2023 | 2052/2053 | Planned replacement 2022/2023 |
| Community Concrete Repairs | 2023 | In Progress Now | |
| Repair Retaining Wall | 2023 | In Progress Now | |